11/06/2022 4:58 pm
A team member is always late to work. The project manager is concerned that this may affect the motivation of other team members. The project manager tells the new team member to align with the team's principles and arrive on time
What kind of conflict resolution did the project manager apply in this situation?
- A . Smooth/accommodate
- B . Compromise/reconcile
- C . Collaborate/problem solve
- D . Force/direct
Suggested Answer: D