What is the protect manager's first step in addressing the problem?

1 Posts
1 Users
0 Likes
241 Views
(@hevesywilber)
Noble Member
Joined: 2 years ago
Posts: 682
Topic starter  

Early prototypes developed in a project show an unacceptably high detect rate. The quality management plan calls for a cause-and-effect analysis to address quality problems as they arise.

What is the protect manager's first step in addressing the problem?

  • A . Communicate the issue to the change control board (CCB) and relevant stakeholders identified in the stakeholder engagement plan
  • B . Create a problem-solving team from quality assurance subject matter experts (SMEs) experienced in this type of analysis
  • C . Form a brainstorming team from project team members selected for their relevant technical analytical and management knowledge
  • D . Form a brainstorming team with stakeholders from all of the functional departments involved in the project

Show Answer Hide Answer

Suggested Answer: D

   