Early prototypes developed in a project show an unacceptably high detect rate. The quality management plan calls for a cause-and-effect analysis to address quality problems as they arise.
What is the protect manager's first step in addressing the problem?
- A . Communicate the issue to the change control board (CCB) and relevant stakeholders identified in the stakeholder engagement plan
- B . Create a problem-solving team from quality assurance subject matter experts (SMEs) experienced in this type of analysis
- C . Form a brainstorming team from project team members selected for their relevant technical analytical and management knowledge
- D . Form a brainstorming team with stakeholders from all of the functional departments involved in the project
Suggested Answer: D