A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint A team member provided ideas to improve the testing process during the sprint retrospective.
What is the next step for the project manager?
- A . Document the lessons learned and implement improvements in the next sprint
- B . Facilitate a daily standup with the team to track the implementation of changes
- C . Organize a demonstration of the changes in the enterprise system
- D . Request that all team members think of ideas to improve processes.
Suggested Answer: A