On a transformational project, the project manager is confronted with resistance from the stakeholders.
To overcome this and gain acceptance of the change, what should the project manager do first?
- A . Escalate the issue to the project sponsor.
- B . Review the stakeholder engagement plan.
- C . Update the issue log.
- D . Neutralize the negative stakeholders.
Suggested Answer: B