A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market
How should the project manager address this issue?
- A . Assess the business value impact and review the product roadmap to include any changes
- B . Schedule a retrospective to understand why the new requirement was not included in product backlog previously
- C . Stop the product release and start adding new user stones to the product backlog for any new requirements
- D . Proceed with product delivery as planned and start a new requirement analysis for the next iteration
Suggested Answer: D