A project manager is assigned to a project that is in development As the project manager reviews the projects progress, they find a few tasks that are behind schedule After investigating the project manager discovers that a few team members were pulled to work on other assignments, which impacted their ability to focus on the project manager’s project
Which two actions can the project manager take to bring the team back on track? (Choose two)
- A . Establish daily standups to review project progress and track the completion of deliverables
- B . Allow the team members to catch up at their own pace
- C . Alert the business stakeholders immediately of the schedule delay.
- D . Discuss the risk of project delay and work priorities with the respective functional managers
- E . Work with the team to identify options to accelerate project delivery.
Suggested Answer: D