During a regular project progress meeting, the CEO informed the project manager that a major stakeholder has been unaware of recent developments on the project. The project manager is sure that the stakeholder was duly identified and classified in the stakeholder register.
Which project document should the project manager review in order to determine the reason for this issue?
- A . Requirements traceability matrix
- B . Stakeholder register
- C . Stakeholder engagement assessment matrix
- D . Issue log
Suggested Answer: C