A project has recently Kicked off. The project manager observes that thete are different expectations among the project team members. These growing misunderstandings are affecting team productivity.

Which document should the project managefve?

  • A . Project charter
  • B . Stakeholder register
  • C . Team charter
  • D . Project organization charts

Show Answer Hide Answer

Suggested Answer: C

   