Two functional managers disagree on key features of one deliverable during the planning of a project. The project manager discovers that each manager included requirements that contradict each other. The functional managers do not want to meet with each other to find a solution This situation has been escalated to the sponsor who requests a meeting with them
What strategy should the project manager use to resolve this conflict in the meeting?
- A . Explain to the managers that the contradicting requirements are being considered for implementation in the project
- B . Explain to the managers that only one of the two requirements can be implemented, and submit a change request,
- C . Ensure that both managers understand the requirements and search for a solution that best satisfies this deliverable
- D . Request that the managers explain why each requirement must be implemented and decide by considering the cost and benefits
Suggested Answer: C