What should the team do next?

1 Posts
1 Users
0 Likes
134 Views
 Man
(@shortinoman)
Noble Member
Joined: 2 years ago
Posts: 733
Topic starter  

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint.

The burndown chart is shown below .

What should the team do next?

  • A . Continue with the sprint as the progress shows buffers for potential interruptions.
  • B . Ask the product owner if some low-priority stories could be cut from the sprint.
  • C . Continue with the sprint work as planned and keep monitoring.
  • D . Ask the project team to select any additional stories as they have additional capacity than planned.

Show Answer Hide Answer

Suggested Answer: C

   