What should the project manager propose?

1 Posts
1 Users
0 Likes
111 Views
(@tivisantwan)
Noble Member
Joined: 2 years ago
Posts: 716
Topic starter  

Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.

What should the project manager propose?

  • A . Develop requirements and designs to support a faster product release.
  • B . Emphasize the adoption of a predictive approach to minimize ambiguity.
  • C . Recommend an agile approach so the project can be delivered iteratively.
  • D . Outsource development of the product to a third party with more experience.

Show Answer Hide Answer

Suggested Answer: C

   