What should the project manager have done differently to avoid the implementation failure?

1 Posts
1 Users
0 Likes
157 Views
(@rippesteban)
Noble Member
Joined: 2 years ago
Posts: 727
Topic starter  

A large organization decided to adopt an agile methodology based on the trends seen in the industry. The organization invested a large amount of money in adopting it, but after a few months, the implementation failed.

What should the project manager have done differently to avoid the implementation failure?

  • A . Conducted agile training for all employees ranging from the project teams through mid-level to upper-level management.
  • B . Conducted a postmortem and captured the learning in organizational process assets (OPAs) for future use.
  • C . Assessed the organization's culture, performed a suitability analysis, and determined the future state.
  • D . Hired a third-party agile delivery team to do the implementation.

Show Answer Hide Answer

Suggested Answer: C

   