UESTION NO: 519
An important email from a project sponsor states that a backlog item should be immediately prioritized .
What should the project manager do with many tasks still open on the Kanban board?
- A . Decompose the item immediately and begin work.
- B . Discuss the impact of starting the item with the team.
- C . Finish the small tasks in progress before decomposing the item.
- D . Communicate the impact with the project sponsor.
Suggested Answer: B