One deliverable for a project is to translate and print materials for students every 2 weeks Printing services are available but without guaranteed time lines because other projects make a significantly higher profit and have a higher priority
What should the project manager do to mitigate the risk of not having the materials printed on time?
- A . Meet with the manager to set a high priority for printing the materials
- B . Create a change request to modify the print requirements
- C . Include a risk response in the resource management plan
- D . Purchase a high-volume printer specifically for this project.
Suggested Answer: C