A team is given an agile project to build a conceptual product for a new customer.
While planning, the project manager is trying to determine the best way to show value to the customer, as the technical requirements are not very detailed.
What should the project manager do to help the client understand the value delivered during project execution?
- A . Include a planned value (PV) calculation in the sprint report for each build cycle.
- B . Conduct a customer demonstration at the end of each build cycle.
- C . Provide the customer with the refined specification during each build cycle.
- D . Show the customer a sprint burndown chart for each build cycle.
Suggested Answer: B