In an agile product development environment, work is distributed to Cities A, B, and C, which are geographically dispersed.
The small teams work and collaborate to deliver the sprints.
• City A's team focuses on the features of data capture.
• City B's team focuses on the user experience and development pieces.
• City C's team coordinates testing.
What should the project manager do to ensure a successful rollout of sprints?
- A . Ensure all three teams deliver independently without interactions so that they remain focused and meet customer requirements.
- B . Implement communication techniques and ensure the teams follow a relay pattern of handing off work from one team to the other.
- C . Use a fishbone analysis to resolve problems and iron out communication issues between the teams.
- D . Maintain localized teams to circumvent the challenges of delay or any other unforeseen risks that might prevent progress.
Suggested Answer: B