What should the project manager do to ensure a successful rollout of sprints?

1 Posts
1 Users
0 Likes
137 Views
 Tuan
(@shippertuan)
Noble Member
Joined: 2 years ago
Posts: 713
Topic starter  

In an agile product development environment, work is distributed to Cities A, B, and C, which are geographically dispersed.

The small teams work and collaborate to deliver the sprints.

• City A's team focuses on the features of data capture.

• City B's team focuses on the user experience and development pieces.

• City C's team coordinates testing.

What should the project manager do to ensure a successful rollout of sprints?

  • A . Ensure all three teams deliver independently without interactions so that they remain focused and meet customer requirements.
  • B . Implement communication techniques and ensure the teams follow a relay pattern of handing off work from one team to the other.
  • C . Use a fishbone analysis to resolve problems and iron out communication issues between the teams.
  • D . Maintain localized teams to circumvent the challenges of delay or any other unforeseen risks that might prevent progress.

Show Answer Hide Answer

Suggested Answer: B

   