A project manager has been hired to help coordinate an ongoing project Historically the biggest problem as reported by the company's CEO is that the change request process has been handled by managers who did not have dear information on the project schedule and budget. This information has been inconsistent and handled by finance, risk. and functional subject matter experts (SMEs)

What should the project manager do to control this situation?

  • A . Redefine the communications management plan
  • B . Develop an integrated change management plan
  • C . Document the risk in the project risk register
  • D . Review the scope defined in the project charter

Show Answer Hide Answer

Suggested Answer: B

   