At the daily project meeting, team members are complaining about receiving emails from their functional managers to support other nonproject-related tasks. This is having a negative impact on the team's productivity.
What should the project manager do next?
- A . Ask the product owner to speak with the functional managers to ensure future requirements come through the product owner.
- B . Log this as a risk in the risk register and continue to monitor the issue at subsequent meetings.
- C . Address this concern with the functional managers to ensure there will be no further delays.
- D . Schedule a meeting with all of the functional managers to resolve the resource conflicts.
Suggested Answer: C