A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative.
What should the project manager do next?
- A . Review organizational process assets (OPAs) for clarity.
- B . Document lessons learned before closing.
- C . Consult the project charter for next steps.
- D . Confirm the definition of done (DoD) has been met.
Suggested Answer: B