A project stakeholder has expressed concern that the established success criteria for the project are not being met .

What should the project manager do next?

  • A . Review the established project benefits tracking metrics.
  • B . Update the project business case document.
  • C . Document the agreed-upon ownership of benefits realization.
  • D . Create a project benefits management plan.

Show Answer Hide Answer

Suggested Answer: A

   