A project stakeholder has expressed concern that the established success criteria for the project are not being met .
What should the project manager do next?
- A . Review the established project benefits tracking metrics.
- B . Update the project business case document.
- C . Document the agreed-upon ownership of benefits realization.
- D . Create a project benefits management plan.
Suggested Answer: A