What should the project manager do in this situation?

1 Posts
1 Users
0 Likes
123 Views
(@hevesywilber)
Noble Member
Joined: 2 years ago
Posts: 682
Topic starter  

A company has always acquired very specialized services from local companies for its projects. During the planning stage for a regulatory project, the project manager is informed that local vendors would not be able to operate due to an unexpected major event. There is an option to hire the same services from companies in other countries.

What should the project manager do in this situation?

  • A . Plan to execute the procurement tasks in a virtual environment.
  • B . Review organizational process assets (OPAs) for similar projects.
  • C . Create a change request to extend the duration of the project.
  • D . Ask the project sponsor to put the project on hold.

Show Answer Hide Answer

Suggested Answer: A

   