What should the project manager do in response to this request?

1 Posts
1 Users
0 Likes
127 Views
(@hepnerjacques)
Noble Member
Joined: 2 years ago
Posts: 705
Topic starter  

A company has hired a vendor to deliver a scope of work and assigned a project manager to oversee the project. The vendor advised that they completed the scope successfully and is asking for approval.

What should the project manager do in response to this request?

  • A . Obtain approval from the project sponsor.
  • B . Update the project management plan and mark the milestone as completed.
  • C . Ask the vendor to validate the agreement for any deviations.
  • D . Set up a meeting with stakeholders to validate and confirm acceptance of the deliverables.

Show Answer Hide Answer

Suggested Answer: D

   