What should the project manager do first to maintain the project team's performance level?

1 Posts
1 Users
0 Likes
79 Views
(@tsuchiuramanual)
Noble Member
Joined: 2 years ago
Posts: 747
Topic starter  

A project team with a tight schedule has succeeded in maintaining a schedule performance index (SPI) of the through regular daily standups and overtime, when required After a few months the project manager notices that some of the team members' performance has decreased but mat the overall project team performance is still ahead of schedule by a few days

What should the project manager do first to maintain the project team's performance level?

  • A . Initiate a performance-based bonus for the team members to provide them with a monetary incentive
  • B . Remind the team frequently that the project must be delivered on time and within budget
  • C . Invite the team to a team-building event to alleviate their stress while strengthening teamwork
  • D . Provide routine mentoring and coaching to the team members to identify any demotivating issues

Show Answer Hide Answer

Suggested Answer: D

   