Notifications
Clear all
Topic starter
31/10/2022 3:50 am
A project team with a tight schedule has succeeded in maintaining a schedule performance index (SPI) of the through regular daily standups and overtime, when required After a few months the project manager notices that some of the team members' performance has decreased but mat the overall project team performance is still ahead of schedule by a few days
What should the project manager do first to maintain the project team's performance level?
- A . Initiate a performance-based bonus for the team members to provide them with a monetary incentive
- B . Remind the team frequently that the project must be delivered on time and within budget
- C . Invite the team to a team-building event to alleviate their stress while strengthening teamwork
- D . Provide routine mentoring and coaching to the team members to identify any demotivating issues
Suggested Answer: D