A project manager is working with an agile team to enhance a product. Due to a tight deadline, the team is trying to crash the schedule by engaging multiple resources to work on the project simultaneously. However, the technical environment is configured to allow only one resource to work on a feature at a time. The team plans to upgrade the technical environment but is unable to agree on a way forward.
What should the project manager do first?
- A . Conduct a consensus-building session to decide how to approach the next set of work.
- B . Escalate the issue to the product owner for resolution.
- C . Add this conflict to the agenda for discussion at the next daily standup meeting.
- D . Conduct a planning session to decide how to approach the next set of work.
Suggested Answer: D