What should the project manager do first?

1 Posts
1 Users
0 Likes
286 Views
(@tivisantwan)
Noble Member
Joined: 2 years ago
Posts: 716
Topic starter  

A project manager is assigned midway through a project. The team members are in different locations across the country and they are unable to meet in-person often. During a status review meeting, one of the stakeholders highlighted that they were unaware of the status for the project deliverables.

What should the project manager do first?

  • A . Request the project team include the stakeholder's details and make sure the project status reports are shared with the stakeholder.
  • B . Schedule a meeting with the stakeholder and include the stakeholder's needs in the project management plan.
  • C . Review the stakeholder management plan and update the stakeholder register for incorporation in the project management plan.
  • D . Review the communications management plan and verify whether the stakeholder's needs are captured in the project management plan.

Show Answer Hide Answer

Suggested Answer: D

   