A project team that is very experienced in enterprise resource planning (ERP) systems implementation is currently planning the delivery of a new ERP project. There is a requirement to reuse the client's security subsystem developed by a third party. The client states that integration with the security subsystem must be done by the client's team. The project manager does not want to have such an external dependency.
What should the project manager do first?
- A . Plan the implementation of this integration in the first iteration to help reduce risks.
- B . Record the issue in the issue log and closely manage this dependency.
- C . Inform the client that the project team will take care of the integration.
- D . Document the client's responsibility for the integration with the security subsystem.
Suggested Answer: D