A company that is introducing a new product into the market by the end of the year requires a storage and distribution facility to be built. During the monthly stakeholder meeting, it is discovered that the location for implementation is a government-owned area
What should the project manager do first?
- A . Identify an alternative site.
- B . Update the issue log
- C . Issue a change request
- D . Update the risk register.
Suggested Answer: D