What should the project manager do first?

1 Posts
1 Users
0 Likes
165 Views
(@casausisaiah)
Noble Member
Joined: 2 years ago
Posts: 710
Topic starter  

A new team member joins an agile team. In a previous role, this team member was a subject matter expert (SME). This team member often directs the team on how to solve problems based on previous experience.

What should the project manager do first?

  • A . Update the definition of done (DoD) to include a review by the new team member to ensure the best outcome of each deliverable.
  • B . Ask the new team member to create a wiki that the rest of the team can reference in the future for all questions.
  • C . Ask the new team member to size all the stories in the backlog so that the rest of the team can focus on delivery.
  • D . Let the new team member know that even if they know the answer, it is better to give the team a chance to solve their own problems

Show Answer Hide Answer

Suggested Answer: D

   