A new team member joins an agile team. In a previous role, this team member was a subject matter expert (SME). This team member often directs the team on how to solve problems based on previous experience.
What should the project manager do first?
- A . Update the definition of done (DoD) to include a review by the new team member to ensure the best outcome of each deliverable.
- B . Ask the new team member to create a wiki that the rest of the team can reference in the future for all questions.
- C . Ask the new team member to size all the stories in the backlog so that the rest of the team can focus on delivery.
- D . Let the new team member know that even if they know the answer, it is better to give the team a chance to solve their own problems
Suggested Answer: D