What should the project manager do?

1 Posts
1 Users
0 Likes
139 Views
(@ripaharris)
Noble Member
Joined: 2 years ago
Posts: 737
Topic starter  

A team is entering into a forming stage after kickoff, with project objectives identified and team members assigned with roles and responsibilities. However, during the team meetings, a team member does not agree on project documents and makes comments that could affect the performance of other team members.

What should the project manager do?

  • A . Escalate the team member's disruptive behavior to their functional manager.
  • B . Collaborate with the team to arrive at team ground rules and publish the rules to the team.
  • C . Observe to ensure this typical forming stage behavior does not escalate beyond what is acceptable.
  • D . Request team members document their decisions independently and share with each other.

Show Answer Hide Answer

Suggested Answer: C

   
Quote