Notifications
Clear all
Topic starter
02/08/2022 1:42 pm
A project manager is leading a project that will be delivered using a Scrum framework. The organization has an innovative project management office (PMO) that fully supports agile and also has a very friendly procurement team. A new vendor needs to be engaged to provide more developers for a new reporting platform.
What should the project manager do?
- A . Use an agile approach and engage a vendor that delivered well in a previous organization.
- B . Consult the product owner and engage a vendor that is recommended by them.
- C . Consult the development team and engage a vendor that is recommended by them.
- D . Use a formal approach using procurement policies, procedures, forms, and work instructions.
Suggested Answer: D