A project manager is leading a hybrid project. The only available resources that have experience with agile are not at the project manager's location. The project has a strict schedule and budget, and the project manager is concerned about their ability to deliver it.
What should the project manager do?
- A . Request a budget extension to get local resources experienced in agile.
- B . Plan to have the agile resources temporarily relocate to the project manager's location.
- C . Engage the agile resources through video conferencing on a daily basis.
- D . Advise the sponsor that the project will be delayed as agile training will be required.
Suggested Answer: C