During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining
What should the project manager do?
- A . Work with the team to understand and solve the issues
- B . Provide testing training to all the project team members
- C . Increase the sprint duration so the testing can be completed
- D . Add a new resource with testing skills to the team
Suggested Answer: B