What should the project manager do?

1 Posts
1 Users
0 Likes
88 Views
(@rippebrain)
Noble Member
Joined: 2 years ago
Posts: 721
Topic starter  

A project manager is assigned to a project that has a tight schedule. Due to recent market changes the marketing team has identified that a few features that were initially in the scope are no longer required

What should the project manager do?

  • A . Advise the marketing team that at this stage of the project changes to the scope are no longer accepted
  • B . Escalate the issue to the project management office (PMO) and make sure they understand the impact on the schedule due to the change
  • C . Update the risk register with input from marketing and sales and highlight the benefits of the features m discussion
  • D . Review the change request with the project stakeholders and evaluate the impact of the scope reduction

Show Answer Hide Answer

Suggested Answer: D

   