What should the project manager do?

1 Posts
1 Users
0 Likes
158 Views
(@pochethurman)
Noble Member
Joined: 2 years ago
Posts: 704
Topic starter  

A project manager and project team have brought a project back on track after mapping and removing impediments During the current sprint the team reported that an impediment that previously caused major delays has appeared again. The team tried implementing the same mitigation tasks that worked previously However, the tasks are not having the same result with the impediment

What should the project manager do?

  • A . Escalate the issue with an impediment to the project sponsor
  • B . Use the contingency budget to implement schedule compression
  • C . Implement the mitigation plans listed in the organizational process assets (OPAs)
  • D . Reassess the issue as part of monitoring and controlling

Show Answer Hide Answer

Suggested Answer: D

   