21/09/2022 12:22 am
A new project manager is managing a hybrid project. The project manager wants to be a servant leader to support the team by removing impediments but is not receiving feedback from the team about the issues and risks they are facing.
What should the project manager do?
- A . Implement daily standups where the team can share their impediments, risks, and issues.
- B . Review the communications management plan and implement changes.
- C . Schedule weekly risk review meetings with the team to review project risks and concerns.
- D . Distribute a copy of the communications management plan to the scrum master.
Suggested Answer: A