A project team member reads in a financial newspaper that the main project supplier is facing some financial difficulties and communicates this to the project manager .
What should the project manager do?
- A . Add the situation to the project risk register to be managed
- B . Identify competitors that are qualified to replace the current supplier
- C . Inform the purchasing department that manages the supplier relationship
- D . Use the issue log to record the situation immediately
Suggested Answer: D