Experienced team members assigned to a critical project are also supporting several other projects and this is delaying the critical project. If this critical project is not delivered, the company could receive a fine from the government .
What should the project manager do?
- A . Discuss the issue with the project sponsor.
- B . Review the resources required for the tasks on the critical path.
- C . Review and update the risk management plan.
- D . Allocate resources to develop the competencies of the other team members
Suggested Answer: B