A project manager works for a large manufacturing company with diversified domains. The project team often participates in change requests Recently, the change control board (CCB) deferred some requests and the project manager wants to communicate these requests to the stakeholders
What document should the project manager use to communicate these requests?
- A . Risk log
- B . Change log
- C . Backlog
- D . Issue log
Suggested Answer: B