The project manager of a hybrid project learns that a stakeholder has approached a team member directly to request a change This change will impact the project m a significant way.
The project manager should ten the stakeholder that the correct procedure tor new requirements is to provide a request directly to whom?
- A . Product owner
- B . Change control board (CCB)
- C . Project sponsor
- D . Project manager
Suggested Answer: D