The project manager of a hybrid project learns that a stakeholder has approached a team member directly to request a change This change will impact the project m a significant way.

The project manager should ten the stakeholder that the correct procedure tor new requirements is to provide a request directly to whom?

  • A . Product owner
  • B . Change control board (CCB)
  • C . Project sponsor
  • D . Project manager

Show Answer Hide Answer

Suggested Answer: D

   