How should the project manager proceed to schedule the kick-off meeting?

1 Posts
1 Users
0 Likes
135 Views
(@cainsmarshall)
Noble Member
Joined: 2 years ago
Posts: 692
Topic starter  

At the end of planning a new project, the project manager needs to schedule the kick-off meeting but is having difficulty finding a common time slot when all necessary stakeholders can be available onsite .

How should the project manager proceed to schedule the kick-off meeting?

  • A . Email all stakeholders with the objectives of the project and ask for feedback.
  • B . Wait for a date when all required attendees can be available onsite.
  • C . Run separate meetings to accommodate everyone's schedule.
  • D . Schedule a virtual meeting so onsite and remote stakeholders can attend at the same time.

Show Answer Hide Answer

Suggested Answer: D

   