How should the project manager influence the team to accomplish the project objectives?

1 Posts
1 Users
0 Likes
75 Views
(@tsuchiuramanual)
Noble Member
Joined: 2 years ago
Posts: 747
Topic starter  

A project manager was just assigned to a project as the leader of an experienced agile team .

How should the project manager influence the team to accomplish the project objectives?

  • A . Express trust in the team's ability to fulfill the necessary deliverables.
  • B . Assert judgment over the team.
  • C . Use a plan-driven approach in order to demonstrate control over the project.
  • D . Increase the amount of subject matter experts (SMEs) to get better results.

Show Answer Hide Answer

Suggested Answer: A

   