During project planning, a development team is assigned an agreed-upon work package to determine the appropriate pattern for integrating a new service with a legacy system. The lead developer has requested a meeting with the project manager and Is looking for direction as to which technology to select.
How should the project manager help guide the lead developer?
- A . Advise the lead developer and team to consult with the project architect and for their development team leader.
- B . Reassign this work package to another area given the lead developer's concerns,
- C . Direct the lead developer to conduct a weighted evaluation of all products and solutions.
- D . Listen to the concerns and suggest that the lead developer and the team be empowered to recommend the best approach.
Suggested Answer: D