How should the project manager handle this situation?

1 Posts
1 Users
0 Likes
162 Views
 Ali
(@ferdigali)
Noble Member
Joined: 2 years ago
Posts: 698
Topic starter  

After a project learn has been working on a project for several months, the project Is cancelled. The project sponsor Is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project.

How should the project manager handle this situation?

  • A . Comply with the project sponsor's request to not archive the project artifacts.
  • B . Document the project sponsor's instructions as the archived project artifacts.
  • C . Archive the project artifacts on the project manager's local computer for future reference
  • D . Consult with the project management office (PMO) for guidance on project artifacts.

Show Answer Hide Answer

Suggested Answer: D

   