A subcontracting company is presenting its feature release A key stakeholder is asking to add a new feature to the product.
How should the project manager deal with the new requirement?
- A . Follow the change management process and work with procurement if needed
- B . Engage an arbitrator to resolve any conflict while handling the new requirement
- C . Add the change to the next sprint to meet the customer's needs
- D . Allocate resources to work on the new feature immediately to complete the request
Suggested Answer: A