A project manager for an agile project wants to have a highly engaged team .

How should the project manager achieve this objective?

  • A . Be clear with directions and assignments so people stay focused and engaged with their work.
  • B . Promote an environment where everybody knows what their contribution means to the project as a whole.
  • C . Design a reward system to get people motivated by recognizing significant individual contributions from the last sprint
  • D . Encourage continuous rotation of roles among team members to keep people motivated throughout project delivery.

Show Answer Hide Answer

Suggested Answer: C

   