Which of the following should the project manager tell the stakeholders?

1 Posts
1 Users
0 Likes
153 Views
(@mcgruenathaniel)
Posts: 732
Noble Member
Topic starter
 

In the review of a project status report, the slack is negative.

Which of the following should the project manager tell the stakeholders?

  • A . The project is behind schedule
    B. The project is over budget
    C. The project has float available
    D. The project needs a gate review

Show Answer Hide Answer

Suggested Answer: A
 