A project manager is justifying a required change with the associated impact on the project.

Which of the following is the NEXT step?

  • A . Implementation
    B. Approval
    C. Validation
    D. Auditing

Show Answer Hide Answer

Suggested Answer: B

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 294
 