The constraint desc...
 
Notifications
Clear all

The constraint described in this scenario is:

1 Posts
1 Users
0 Likes
102 Views
(@whellerrashad)
Posts: 729
Noble Member
Topic starter
 

A project team started work on a project and was ahead of schedule when the project sponsor announced that the project needed to stop because of shifting strategic priorities.

The constraint described in this scenario is:

  • A . cost
    B. environmental
    C. scope
    D. scheduling

Show Answer Hide Answer

Suggested Answer: C
 