A project manager has been asked to prepare and present a review of the execution phase.

Which of the following is the BEST audience for this review?

  • A . Vendors
    B. Key stakeholders
    C. Resources
    D. Project team
    E. Business analysts

Show Answer Hide Answer

Suggested Answer: D
 