A project team has determined it will need to source data from a system that was not part of the project scope.
The role of the project manager is to analyze which of the following impacts?
- A . Technical design, schedule, and budget
B. Business process impacts and resourcing
C. New software and hardware requirements
D. Schedule, budget, and quality
Suggested Answer: C